Utilization is a powerful tool to help you optimize staffing projects and efficiently manage employees to achieve peak performance on every job.

Creating a New Workforce Shift

As soon as an Opportunity is entered into Buildr and given a start and end date, you have the ability to start assigning shifts to employees. For this example, we created an Opportunity called, "Rincon Marine Biology Research Lab".

In the Opportunity, navigate to the Workforce Tab and select the New Shift button.

Assign the Shift Start/End dates, the Role, and set the Utilization Percentage.

In this example, we set the utilization to 50%. This means that 50% of their time is allocated to this project. So for example, 20 hours in a 40 hour work week would go to this job.

If the job requires 100% of their time, then set it to 100%. If 25% of their time, than 25%, etc. You can also go back and update this information later if you anticipate this changing.

After you finish entering your workforce shifts, you will see a summary of these under the Workforce tab in the Opportunity, and the utilization for each employee will be visible in its own column:

From there, you can click "Assign Employees" in order to pick a specific person to fill each role. You can also do this by navigating to Workforce > Shifts, and by clicking on a specific Shift.

Shift Assignment Modal

When you assign a shift, you will see your list of employees on the left side as shown in the image below. Search for and select an employee to see their Availability and determine if assigning them to this specific Opportunity will work. Compare availability and utilization to see who will be the best fit for the assignment.

For this example, we assigned Casey Schmidt to the Project Manager role on the Rincon Marine Biology Research Lab as shown above.

The bars at the very top of the Availability section (the gray, green, and blue stripe bars; each color is defined below the next image) indicate the total utilization in light of the current shift you are trying to assign. Each segment represents a change in availability. If you hover over each bar, it will show the total utilization for that time period, the dates of that time period, and the number of days.

Casey does not have availability for the start of this project as shown by the gray bars, so let's move onto a different employee. The next one down, Mitchell Spencer, also does not have availability for a portion of the project, but we'll select him to so we can dive more into what each color bar specifically means when assigning shifts.

Explanation of the Colors in the Shift Assignment Modal

  • The green bars indicate that assigning the employee to the shift will work because the total utilization will be 100% or less during that time period. Here are some examples of when the green will show up in the Availability window:

    1. The employee is not assigned to any projects

    2. The employee is assigned to a project that requires less than 100% utilization AND the shift you are trying to assign does not cause the employee to exceed 100% utilization. So if they are assigned to Project 1 at 50% utilization and you are trying to assign them to a shift on Project 2 that requires 50% utilization (or less), then the bar will appear green.

  • The gray bars indicate that the assignment will not work because the assignment will cause the employee's utilization to exceed 100% during this time OR they are already 100% utilized on other projects.

  • The blue stripe bars indicates that the employee is available but assigned to other pursuits at during that time period (in the photo above, Mitchell is assigned to Healthcare Office Building (Shell), which is an Opportunity that is either in the Discovery, Proposal, or Contract sent stage). Pursuits are not guaranteed, so blue bar means that assigning the employee to the shift works tentatively, but its possible that changes if the opportunity moves from a pursuit stage to the Won stage.

Accessing the Shift Assignment through Workforce Shifts

If we navigate to Workforce > Shifts, then we will see that the role has been filled and employee's name is listed under the Rincon Marine Biology Research Lab Opportunity.

If you click on the shift in the Gantt Chart view (the purple bar), it will pull up the Shift Assignment Modal that we saw previously.

Availability Section in the Shift Assignment Modal Explained

If you hover over any of the availability bars or bars that represent individual opportunities in the shift assignment modal, more specific information shows up. For this example, we assigned a new employee (Meghan) to the Project Manager shift on the Rincon Marine Biology Research Laboratory opportunity.

In the image below, we pulled up the Shift Assignment Modal and moused over the "Northstar Building B" project. We see the Stage, Start and End Dates, Utilization %, and Role for the employee on this opportunity.

Meghan is 100% utilized on the Northstar Building B project, and this project is in the "Won" stage. This will be reflected in the total utilization percentage.

If we mouse over the Rincon Marine Biology Research Lab project (shown in the image below), we see that Meghan is assigned to 50% utilization. This project overlaps with the Northstar Building B project (which requires 100% utilization), so the total utilization will be over 100% if we win the opportunity.

However, because this Opportunity is not yet set to the "Won" stage, the total utilization percentage is not affected yet when we hover over the gray bar, which shows the total utilization:

So even though Meghan would be over-utilized during this time period, it does not show up yet because the Rincon Marine Biology project has not been Won. The bar is gray to indicate that assigning her to this shift on the Rincon opportunity will not work because she is 100% utilized on the Northstar Building B opportunity.

Let’s say we win this job and change the Opportunity to the “Won” stage. The total utilization of the employee will update to 150% now that opportunity is Won, and it will show that Meghan is over-utilized.

We can then reassign the Project Manager role within the Shift Assignment Modal to find someone who has the availability to start the Rincon project so that Meghan's utilization stays at 100% and so that another employee is properly utilized.

Simply choose another employee that shows up in the left who has availability: